The total amount of work (in story points) an Agile development team completes successfully during a single Sprint is called:

ACycle Rate
BTeam Velocity
CThroughput Index
DBurn Capacity

Explanation

Velocity measures the rate of work delivery per Sprint and is used to estimate future release timelines.