The initial setting time of standard Ordinary Portland Cement (OPC) should not be less than:

A15 minutes
B30 minutes
C60 minutes
D600 minutes

Explanation

As per standard codes (IS 269 / BS 12), initial setting time of OPC should not be less than 30 minutes, and final setting time should not exceed 600 minutes (10 hours).