The initial setting time of Ordinary Portland Cement (OPC) should not be less than:

A15 minutes
B30 minutes
C45 minutes
D60 minutes

Explanation

According to standard cement specifications, the initial setting time of Ordinary Portland Cement (OPC) must not be less than 30 minutes to allow adequate time for mixing, transporting, and placing. The final setting time must not exceed 600 minutes (10 hours).