Which management tool uses network diagrams and critical path analysis to plan, schedule, and control complex project tasks?

AGantt Chart
BPERT / CPM
CFishbone Diagram
DPareto Chart

Explanation

• PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) use network models to map activity sequences and dependencies.
• The Critical Path represents the longest sequence of dependent activities, determining minimum project completion time.
• Activities on the critical path have zero float (slack time).

Exam Relevance
  • Topic: Operations & Project Management
  • Subtopic: PERT CPM