If a worker does a job in 20 days and another in 30 days, together they take:
A10 days
B12 days
C15 days
D25 days
Explanation
1/20 + 1/30 = 5/60 = 1/12. Time=12 days.
Exam Relevance
- Topic: Work and Time
- Subtopic: Joint Work