The sequence of dependent project activities that exhibits zero total float (slack) and dictates the earliest possible project completion date is the:

ACritical Path
BSub-critical Path
CFast-track Path
DDummy Path

Explanation

• The Critical Path is the longest path through a project network, determining the minimum total calendar duration needed for project execution.
• Any delay encountered by an activity along the critical path causes an immediate, equal delay to the overall project completion.
• Activities residing on the critical path have Slack/Float = 0.

Exam Relevance
  • Topic: Operations Management
  • Subtopic: Critical Path Method