For a simply supported beam of span ‘L’ loaded with a point load ‘W’ at midspan, the maximum deflection at midspan is given by:

AW L³ / (48 E I)
BW L³ / (3 E I)
C5 W L³ / (384 E I)
DW L³ / (192 E I)
Submitted by: mcqstutor Team 0 comments

The section modulus (Z) of a solid circular cross-section of diameter ‘d’ is equal to:

Api * d³ / 16
Bpi * d³ / 32
Cpi * d⁴ / 64
Dpi * d³ / 64
Submitted by: mcqstutor Team 0 comments

The initial setting time of standard Ordinary Portland Cement (OPC) should not be less than:

A15 minutes
B30 minutes
C60 minutes
D600 minutes
Submitted by: mcqstutor Team 0 comments

In stone masonry, a vertical joint that continues continuously through two or more consecutive courses is called a:

AThrough stone
BContinuous vertical joint (Defect)
CLacing course
DQuoin
Submitted by: mcqstutor Team 0 comments

In concrete mix design, the compaction factor test is specifically suitable for concrete mixes having:

AHigh to very high workability
BLow to medium workability
CZero workability
DSelf-compacting properties
Submitted by: mcqstutor Team 0 comments