What is the total maximum power generation capacity of the Tarbela Dam 5th Extension Hydropower Project in Pakistan?

A1,410 MW
B1,530 MW
C2,400 MW
D4,500 MW

Explanation

• The Tarbela 5th Extension Hydropower Project involves installing generating units on Tunnel 5 of the Tarbela Dam, adding 1,530 MW of clean hydro energy to the national grid.
• Upon completion, Tarbela Dam’s total installed electricity generating capacity will increase from 4,888 MW to 6,418 MW.