The workability of concrete measured by the slump test for heavy mass concrete construction should ideally range between:

A0 to 25 mm
B25 to 50 mm
C75 to 100 mm
D100 to 150 mm

Explanation

For heavy mass concreting (such as dams and massive foundations) compacted by vibrators, low workability with a slump of 25 to 50 mm is preferred to minimize shrinkage and thermal cracking.