The Critical Path Method (CPM) in software project scheduling determines:
AThe sequence of dependent tasks that defines the minimum total time required to complete the project
BThe path with the highest financial cost
CThe tasks with maximum buffer slack time
DThe sequence of unassigned developer tasks
Explanation
The Critical Path represents the longest sequence of dependent activities, determining the earliest possible project completion.
Exam Relevance
- Topic: Software Project Management
- Subtopic: Scheduling