The critical path in a CPM network diagram represents the sequence of activities having:
AMinimum duration
BMaximum total float
CZero total float and maximum duration
DIndependent float equal to activity time
Explanation
In Critical Path Method (CPM) networks, the critical path is the longest continuous chain of activities from start to finish. Activities along this path have zero total float, meaning any delay directly delays project completion.