Tasks located on the Critical Path in a PERT/CPM software project network diagram always have a Total Float of:

AMaximum Float
BPositive Float equal to 10 days
CZero Float
DNegative Float

Explanation

Critical path tasks have zero float (slack time = 0), meaning any delay on these tasks directly delays project completion.