Initial setting time of ordinary Portland cement (OPC) should not be less than:
A10 minutes
B60 minutes
C30 minutes
D600 minutes
Explanation
As per standard cement specifications, initial setting time of Ordinary Portland Cement (OPC) must not be less than 30 minutes to allow mixing and placing, while final setting time must not exceed 600 minutes (10 hours).