In CPM project network planning, Total Float (TF) of an activity is calculated as:

ALatest Start Time (LS) - Earliest Start Time (ES)
BEarliest Finish Time (EF) - Earliest Start Time (ES)
CLatest Finish Time (LF) - Latest Start Time (LS)
DEarliest Start Time of next activity - Earliest Finish Time of current activity

Explanation

Total Float TF = LS – ES = LF – EF. It represents total allowable delay without delaying project completion.