In Agile project management, what chart plots project scope backlog growth alongside sprint completion progress to predict release dates?

ABurndown Chart
BGantt Chart
CControl Chart
DBurnup Chart

Explanation

A Burnup chart tracks total scope changes alongside work completed, making scope expansion clearly visible.