If 8 men can complete a project in 15 days, how many days will 12 men take to complete the same project?

A8 days
B10 days
C12 days
D14 days

Explanation

Using inverse proportion formula M1 * D1 = M2 * D2: 8 * 15 = 12 * D2 => 120 = 12 * D2 => D2 = 10 days.