If 8 men can complete a job in 12 days, how many days will 6 men take to finish the same job?
A14 days
B16 days
C18 days
D20 days
Explanation
M1 * D1 = M2 * D2 => 8 * 12 = 6 * D2 => 96 = 6 * D2 => D2 = 16 days.