If 16 men can complete a project in 15 days, how many men are needed to complete the project in 10 days?

A20
B22
C24
D26

Explanation

M1 * D1 = M2 * D2 => 16 * 15 = M2 * 10 => M2 = 240 / 10 = 24 men.