If 12 men can complete a work in 20 days, in how many days can 15 men complete the same work?

A12 days
B14 days
C16 days
D18 days

Explanation

Using M1 * D1 = M2 * D2: 12 * 20 = 15 * D2 => 240 = 15 * D2 => D2 = 16 days.

Exam Relevance
  • Topic: Work and Time
  • Subtopic: Inverse Proportion