A can do a work in 10 days and B in 15 days. They work together for 3 days and then A leaves. How long will B take to finish the rest?

A5 days
B7.5 days
C8.5 days
D10 days

Explanation

A+B=1/10+1/15=1/6. In 3 days, they do 3/6=1/2. Remaining=1/2. B does 1/2 in (1/2)/(1/15) = 7.5 days.