Pakistan's best MCQs practice hub — FPSC · PPSC · CSS · NTS · Other Exams
Login

What total energy generation capacity does the Karot Hydropower Project under CPEC produce in Azad Jammu and Kashmir?

A720 MW
B870 MW
C1,100 MW
D1,320 MW

Explanation

• The 720 MW Karot Hydropower Project, constructed on the Jhelum River between Rawalpindi district and AJK, is the first hydro investment under CPEC.
• It generates approximately 3.2 billion kilowatt-hours of clean electricity annually, supplying over 5 million people in Pakistan.

Submitted by: mcqstutor Team More Current Affairs MCQs →