In CPM network diagramming, a dummy activity is used to:

ARepresent an activity consuming maximum time and cost
BEstablish logical precedence relationship without consuming time or resources
CConnect initial and final nodes directly
DDelay critical path activities

Explanation

A dummy activity consumes zero time and zero resources. It is introduced purely to maintain logical precedence and unique node numbering.