In project management networks, PERT analysis assumes that activity durations follow which probability distribution?

ANormal Distribution
BBeta Distribution
CPoisson Distribution
DExponential Distribution

Explanation

Program Evaluation and Review Technique (PERT) incorporates uncertainty using three time estimates (Optimistic a, Most Likely m, Pessimistic b) modeled by a Beta probability distribution. Expected time te = (a + 4m + b) / 6.