In PERT network analysis, the probability distribution of event completion time is assumed to follow:

ABeta distribution
BPoisson distribution
CExponential distribution
DNormal distribution

Explanation

Program Evaluation and Review Technique (PERT) accounts for activity duration uncertainty by assuming activity durations follow a Beta probability distribution with optimistic, most likely, and pessimistic estimates.