Pakistan's best MCQs practice hub — FPSC · PPSC · CSS · NTS · Other Exams
Login

If a software task has optimistic estimate $a = 4$ days, most likely $m = 7$ days, and pessimistic $b = 16$ days, its PERT expected duration $T_e$ is:

A7 Days
B9 Days
C8 Days
D10 Days

Explanation

Using formula $T_e = rac{4 + 4(7) + 16}{6} = rac{4 + 28 + 16}{6} = rac{48}{6} = 8 ext{ days}$.

Submitted by: mcqstutor Team More Software Engineering MCQs →

No Comments

Leave a comment

Your email address will not be published. Required fields are marked *