In cost variance analysis, what is the labor rate variance formula?

A(Actual Rate - Standard Rate) * Actual Hours
B(Actual Hours - Standard Hours) * Standard Rate
C(Actual Rate - Standard Rate) * Standard Hours
D(Actual Hours - Standard Hours) * Actual Rate

Explanation

* Labor Rate Variance = (Actual Rate paid per hour – Standard Rate per hour) * Actual Hours worked.
* Favorable if Actual Rate < Standard Rate. * Evaluates wage rate wage negotiations and labor grade assignment choices.

Exam Relevance
  • Topic: Cost Accounting
  • Subtopic: Variance Analysis
Submitted by: mcqstutor Team More Finance & Accounting MCQs →