If 6 men can complete a job in 8 days, how many days will 4 men take?
A10 days
B12 days
C14 days
D16 days
Explanation
M1 * D1 = M2 * D2 => 6 * 8 = 4 * D2 => 48 = 4 * D2 => D2 = 12 days.
Exam Relevance
- Topic: Work and Time
- Subtopic: Inverse Proportion