If a work is completed by 8 workers in 12 days, how many extra workers are needed to finish it in 8 days?
A2
B4
C6
D8
Explanation
Workers needed = (8 * 12) / 8 = 12 workers. Extra workers required = 12 – 8 = 4 workers.